Tentative Building Schedule

If you can join us for any of these days, please RSVP and let us know.

Want to help?

 

Here’s how to RSVP:

  • To help on a Saturday, notify Adam you’re coming that day via text (970-590-0525) or email (adam.bonus@reliancefellowship.org). Work will be 9:00 – 4:00 those days.
  • To help on a weekday, call Adam (970-590-0525) before you come to confirm someone is there when you arrive.
Date Activity Needs
Wed, Mar 15 Finish framing the walls 3-4 people
Sat, Mar 18 Electrical work in new walls, build the sound booth, remove old flooring
Wed, Mar 22 Install double doorway (doors anchored shut)
Fri, Mar 24 Framing inspection, begin sheetrock
Sat, Mar 25 Hang SHEETROCK! Lot of guys, scissor lift
Tues, Mar 28 Sheetrock inspection
W-F, Mar 29-31 Drywall mud & tape Drywall Pro’s
W-F, Mar 29-31 Electrical work (Lighting) Electrician
Sat, Apr 1 Painting 5-6 people
Wed-Fri, Apr 5-7 Build the stage 5-6 people
Mon, Apr 10 Inspection for electrical,

Carpet installation

Carpet Installers
Tues, Apr 11 Final Inspection!
Tues-Thurs Run the audio snake, set up projectors,

Set up chairs, stage, etc.

3-4 people
Sun, April 16 EASTER SUNDAY – 1st service in new area!